Agree the criteria before booking anyone
The single largest cause of disputed inspections is that nobody wrote down what 'acceptable' means. The specification, the sampling plan, the acceptance quality limits, and what counts as a critical, major, or minor defect should all be agreed in writing between buyer and supplier before an inspector is instructed.
Settled afterwards, those same questions become a negotiation with a shipment sitting in the middle of it.
Confirm readiness honestly
Pre-shipment inspection is normally carried out when production is substantially complete and packing is under way. Attend too early and the sample is not representative; too late and there is no time to correct anything before the vessel.
Have the documents on site
An inspector works against reference documents. These should be at the site, not with someone who is travelling:
- The purchase order and any agreed specification or drawing
- Approved samples or a golden sample, where one exists
- Packing and labelling requirements, including barcodes and markings
- Any test certificates or declarations that ship with the goods
- The agreed inspection checklist and sampling plan
Arrange access and people
Access sounds trivial and derails visits regularly. Confirm site entry, safety requirements, whether the inspector can open cartons, whether goods can be unpacked and repacked, and who on site has authority to answer questions.
Treat a fail as information
A report recording nonconformity is a successful inspection — it did what it was commissioned to do, at the point where doing something about it is still cheap. Suppliers who understand that in advance tend to cooperate; suppliers who expect a rubber stamp tend to argue.
Say so when you brief them. It changes the tone of the visit and usually the outcome.